The Build 2021

Concrete and mud

Well, I am managing better. We have the first pour of the foundations and everything is moving a might quicker than expected… They are thinking at the moment of finishing one or two weeks early.

Wow!

Picking up the back garden…
Foundations going in.

Well, there we are then. The garage is being studded and made into a room, and the foundations are drying. All in all, everything is moving fast. Can’t wait for the walls to go in!

On the autistic front, so far the spoon theory has worked and I’ve not had another meltdown. Thank goodness.